What Does a Green Hydrogen Mandate Cost?

Evidence from the Intermountain Power Project

Submitted for peer review · International Journal of Hydrogen Energy (Elsevier) · 2026

Overview

This paper studies the cost of producing hydrogen at the Intermountain Power Project, an 840 MW facility, under a renewable-only requirement. Using 17,544 hours of wholesale electricity price data, calibrated solar and wind generation, and grid-carbon-intensity data, I compare a grid-connected pathway with a renewable-only pathway supported by hydrogen storage.

Key Findings

Method & Analysis

The model compares hydrogen production configurations at a fixed hydrogen output level: a grid-connected pathway and a renewable-only ("island") pathway required to meet the project's green hydrogen mandate, with hydrogen storage used to bridge periods of low renewable output. Electricity costs, calibrated solar and wind generation, and grid carbon intensity are drawn from 17,544 hours of historical data.

Data & Sources

Hourly wholesale electricity price and grid-carbon-intensity data, and renewable technology cost assumptions from the U.S. National Renewable Energy Laboratory's Annual Technology Baseline.

Limitations

Results depend on the specific project configuration, technology-cost assumptions, and historical price data used. They should be read as evidence from this project, not as a general finding for all green hydrogen mandates.

Downloads

Working paper available on SSRN: dx.doi.org/10.2139/ssrn.7428658.

Citation & Status

Status: posted as a working paper on SSRN; submitted for peer review at the International Journal of Hydrogen Energy (Elsevier).

Suggested citation for this working paper (not yet peer-reviewed): Akbar, L. (2026). "What Does a Green Hydrogen Mandate Cost? Evidence from the Intermountain Power Project." Working paper. SSRN. https://dx.doi.org/10.2139/ssrn.7428658. ORCID: 0009-0005-0593-3939.